Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
  • if market-rate construction is delayed, will the affordable housing also be delayed?
  • if so, what happens to the June 2014 agreement, reached by New York State and some community community negotiators, to guarantee--with penalties--the 2,250 units of affordable housing by May 2025, "subject to extensions set forth in the Development Agreement and the General Project Plan"? 
  • will affordable housing be built on sites previously planned for market-rate housing?
  • will covering the railyard for vertical construction be delayed? And doesn't that prolong blight?
  • how much tension is this causing between Forest City and its Shanghai-based partner?
  • beyond the three sites already up for sale/new investment, how much more might be sold?
  • will the developers seek more subsidies, or relaxed terms regarding the affordable housing?
Annotations as of October 2016
The announcement

According to the news release, Forest City, for the three months ended September 30, 2016, had a net loss of $430.9 million, or $1.67 per share, compared with a net loss of $302.2 million, or $1.18 per share, the previous year, mainly due to increased impairments:
The third-quarter net loss includes an impairment of non-depreciable real estate of $307.6 million, primarily related to Pacific Park Brooklyn. During the quarter, in light of changing market conditions directly impacting the Brooklyn residential market, the company, as part of a formal strategic plan update, made the decision to revise the overall project schedule to delay future vertical development. Given these market conditions and project timing, the company updated its estimated revenue, expense, cost and timing assumptions in its discounted cash flow model to estimate fair market value. The updated estimates no longer exceeded the carrying value of the asset, triggering the need for impairment. After the impairment, the company's remaining basis in its aggregate investment at Pacific Park Brooklyn is not material on a GAAP basis.-
(Emphasis added)

Note that Forest City, which is the minority partner in Pacific Park, had to jointly agree with joint venture partner/overseer Greenland USA, which owns 70% of the project/development rights going forward (excepting the arena and the 461 Dean tower). But no mention was made of a joint decision.

In a supplemental document filed with the Securities and Exchange Commission, the developer said that, regarding Pacific Park, it recorded "an impairment of $299.3 million ($266.0 million and $33.3 million allocated our projects under development and projects under construction, respectively."

CEO commentary

"We also recognized a significant impairment of Pacific Park Brooklyn as a result of our decision to revise the project schedule and related assumptions in light of evolving market conditions, including the impact of increased apartment supply, uncertainty surrounding 421A tax abatement and continued escalation in construction and trade costs," Forest City CEO David LaRue said in the statement.

In a separate 10-Q document filed with the SEC, the company added more explanation, acknowledging that the 550 Vanderbilt condo building is delayed:
During the three months ended September 30, 2016, it became evident the occupancy and rental rate declines in the Brooklyn market was determined not to be temporary as a result of an increased supply of new rental product amplified by the sun-setting and the uncertainty around the 421 A real estate tax abatement program. Over the last quarter, the condominium market in New York has also softened, causing the projected sale schedule for 550 Vanderbilt to be adjusted accordingly. Separately, the construction costs across the New York market continue to trend upward, resulting in increases in the estimated trade costs for certain infrastructure as well as vertical construction. In addition, the expiration of and the continued uncertainty related to the availability of the 421 A real estate tax abatement program puts further stress on anticipated returns.. the Company updated the discounted cash flow model to reflect the updated timing of the project schedule as well as the revenue, expense and cost assumptions. Based on the above, the estimated fair value of the investment no longer exceeded the carrying value. As a result, the Company recorded an other-than-temporary impairment of$299,300,000 during the three months ended September 30, 2016. The remaining basis in the investment (net of estimated future funding obligations) is not material.
No updated schedule was announced, but presumably there will be questions during today's conference call with investment analysts.

"While the Pacific Park Brooklyn impairment is a disappointment, revising the schedule to delay additional future vertical development reflects the tough decisions that are part of our disciplined approach to capital allocation," LaRue said. "As we have said before, we will activate new opportunities from our pipeline of entitlements only when and where we believe we can achieve an appropriate risk-adjusted return."

He made no mention of the affordable housing deadline.

Under construction

The press release cites three Pacific Park properties under construction:
  • 535 Carlton, a 298-unit, all-affordable apartment community, is expected to begin phased opening in the fourth quarter of 2016.
  • 550 Vanderbilt, a 278-unit condominium property, is expected to begin phased opening in the first quarter of 2017.
  • 38 Sixth Avenue, a 303-unit, all-affordable apartment community with 6,000 feet of street-level retail, is expected to begin phased opening in the second quarter of 2017.
There seem to be some delays, however. A separate 10-Q document filed with the SEC offers the following timetable. Note that "100% affordable" 535 Carlton could take a year to fill up, until the fourth quarter of 2017, as could the similar 38 Sixth Avenue, starting in the second quarter of 2017. Meanwhile 550 Vanderbilt is supposed to open in the first three quarters of 2017.


Is modular tower open?

The document, oddly enough, said that, in the third quarter of this year, Forest City opened two new properties, including "461 Dean Street, a 363-unit apartment community at Pacific Park Brooklyn."

Actually, it's by no means open. The Supplemental document says construction is complete and that, as of 9/30/16, 160 of the 363 units had received a certificate of occupancy.

According to p. 50 of the Investor Presentation below, as of 10/27/16, the developer has a 3% lease commitment at 461 Dean. Presumably that applies to the 50% market-rate units, and/or the retail, not the 50% below-market "affordable" units, for which there was a lottery.


Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Not quite the pattern: Greenland selling development sites, not completed condos

Real Estate Weekly, reporting on trends in Chinese investment in New York City, on 11/18/15 quoted Jim Costello, a senior vice president at research firm Real Capital Analytics:
“They’re typically building high-end condos, build it and sell it. Capital return is in a few years. That’s something that is ingrained in the companies that have been coming here because that’s how they’ve grown in the last 35 years. It’s always been a development game for them. So they’re just repeating their business model here,” he said. When I read that last November, I didn't think it necessarily applied to Atlantic Yards/Pacific Park, now 70% owned (outside of the Barclays Center and B2 modular apartment tower), by the Greenland Group, owned significantly by the Shanghai government.
A majority of the buildings will be rentals, some 100% market, some 100% affordable, and several--the last several built--are supposed to be 50% market/50% subsidized. (See tentative timetable below.)

Selling development …

Atlantic Yards/Pacific Park graphic: what's built/what might be coming (post-dated pinned post)

Click on graphic to enlarge. This is post-dated to stay at the top of the blog. It will be updated as announced configurations change and buildings launch. The August 2014 tentative configurations proposed by developer Greenland Forest City Partners will change, and the project is already well behind that tentative timetable.